- plumbing rough -in and heating done by the end of the week
- furnaces already hung
- electrical rough in and low voltage wiring done by the end of 2 weeks
- concrete poured by the the end of 2 weeks
- shingles will be completed this week
- siding started anytimestairs inside done next 2 to 3 weeks
- framers back to finish basement framing and other little discrepancies after concrete poured
Monday, September 26, 2011
Sunoka Ranche Update
Take a click on over to my link, and see some new pictures. We were out there just this past Saturday. Dave and I got a bit of a lowdown, this morning at the electrical walk through, to what's going to be happening in the next two weeks or so ( this is in no order...but I'm sure Dave knows the order....I just figure it's gettin' done)